Equipment Tracker
Real-time monitoring of technical infrastructure assets.
Showing 5 Records
| Block | Level | Total Units | Installed | Remaining | Progress | Status | Comments |
|---|---|---|---|---|---|---|---|
| Block A | Level 01 | 45 | 42 | 3 | 93% | Installed | On schedule |
| Block A | Level 02 | 45 | 38 | 7 | 84% | WIP | Ductwork testing underway |
| Block A | Level 03 | 50 | 20 | 30 | 40% | In Transit | Delivery expected Oct 22 |
| Block B | Level 01 | 60 | 60 | 0 | 100% | Installed | Commissioned & signed off |
| Block B | Level 02 | 55 | 10 | 45 | 18% | Delayed | Awaiting damper brackets |